Highway 4 (Crosstown Freeway) Extension Project
Project Description
This project will extend the Cross-town Freeway
west from Fresno
Avenue to Navy Drive.
The improvements would include a four lane
facility, auxiliary lanes, and a partial interchange at Navy Drive.
The extension will be carried on twin viaduct structures that will
cross over Fresno Avenue and create a grade separation that will no
longer allow highway traffic to enter the Boggs Tract neighborhood at Fresno
Avenue. Two alternative configurations of the extension are
currently under consideration. This project would serve as Stage I
of the ultimate extension of the Cross-town freeway to the Port of
Stockton Expressway, west of the San Joaquin River.
aState
Route 4 Crosstown Freeway Ramp Extension Project
Final Environmental Impact Report

Project Location Map (click to enlarge)
| Total Project Cost |
$193.6 Million |
|
| |
| Funding Breakdown: |
|
| Trade Corridor Improvement Fund
| $96.8 Million |
| Measure K |
$93.8 Million |
| Regional Transportation Impact Fees |
$ 3.0 Million |
| Project
Schedule |
|
|
|
| Begin: |
Complete: |
| Environmental
| July 2008 |
November 2010 |
| Design |
June 2010 |
February 2013 |
| Right-of-Way |
August 2010 |
January 2013 |
| Construction |
June 2013 |
June 2016 |
Project Resources (click photos to enlarge)

Port of Stockton Aerial View
Truck Turning on Hwy 4
Project Partners

| Site Map |
Links |
|
555 E. Weber Ave., Stockton CA 95202-2804,
209.235.0600, 209.235.0438 fax |
|