Measure K Renewal Strategic Plan Completion Schedule
The SJCOG Board is scheduled to adopt the Measure K Renewal Strategic
Plan at their October 25th meeting. As identified in the Strategic Plan
completion schedule, a Draft Strategic Plan is being prepared in August
for review with the Strategic Plan Working Group at their August 23rd
meeting. SJCOG staff will be convening a meeting of business and
industry representatives in late August to help ensure that the project
scopes and transportation programs in the Strategic Plan are developed
to appropriately address planned business and industry development
within San Joaquin County. SJCOG staff will also be convening a third
meeting of the Smart Growth Subgroup to finalize elements of the Smart
Growth Incentive Program that will need to be incorporated in the
Strategic Plan.
In September the Draft Strategic Plan will be taken through the standing
SJCOG committees with a SJCOG Board workshop on the Strategic Plan
scheduled for the morning of September 21st. The day prior to the SJCOG
Board workshop, SJCOG staff will be hosting a community meeting on the
Strategic Plan to provide outreach to and seek input from the general
public. Based upon the comments received from the standing committees,
the general public, and the SJCOG Board in September, the Draft
Strategic Plan will be updated and a Draft Final Strategic Plan will be
taken through the standing SJCOG committees in October with final
approval by the SJCOG Board targeted at their October 25th meeting.
At this time the transit program work for this initial plan is largely
completed and it has been agreed with the Strategic Plan Working Group
that the identification of the specific bus transit, bicycle,
pedestrian, and safe route to school program projects will be completed
over the next 18 months, concurrent with the update of local transit
plans and the SJCOG regional transit systems plan. The Smart Growth
Subgroup is on track for their share of the draft strategic plan and
progress is being made on the Railroad Crossing Safety Program with key
decisions and recommendations to be completed at the end of August. The
Strategic Plan Working Group has seen and provided detailed comments on
the state highway portion of the Congestion Relief Program, however,
there is ongoing work with the local agencies to distribute funding
across the regional arterial projects of the Congestion Relief Program.
|
Item |
Task |
Activity |
Completion Date |
|
July |
|
1 |
Meeting of Transit Subgroup |
Review and approval of transit policies for Strategic Plan |
July 16 |
|
2 |
Meeting of Strategic Plan Working Group |
Review and approval of congestion relief and railroad crossing
safety projects and policies for Strategic Plan |
July 19 |
|
3 |
Meeting of Smart Growth Subgroup |
Review of Smart Growth framework for Strategic Plan |
July 27 |
|
August |
|
4 |
Meeting of Strategic Plan Working Group |
Review/discussion of Draft Strategic Plan |
August 23 |
|
5 |
Meeting of Smart Growth Subgroup |
Review and approval of Smart Growth framework for Strategic Plan |
August 24 |
|
6 |
Business and Industry Group Meeting |
Presentation of Draft Strategic Plan |
August 28 |
|
September |
|
7 |
SJCOG Technical Advisory Committee |
Presentation of Draft Strategic Plan |
September 13 |
|
8 |
SJCOG Citizens Advisory Committee |
Presentation of Draft Strategic Plan |
September 19 |
|
9 |
SJCOG Management & Finance Committee |
Presentation of Draft Strategic Plan |
September 19 |
|
10 |
Meeting of Strategic Plan Working Group |
Review of comments on Draft Strategic Plan |
September 20 |
|
11 |
Community Meeting |
Presentation of Draft Strategic Plan |
September 20 |
|
12 |
SJCOG Board Workshop |
Review/comment of Draft Strategic Plan |
September 21 |
|
October |
|
13 |
SJCOG Technical Advisory Committee |
Presentation of Draft Final Strategic Plan |
October 11 |
|
14 |
SJCOG Citizens Advisory Committee |
Presentation of Draft Final Strategic Plan |
October 17 |
|
15 |
SJCOG Management & Finance Committee |
Presentation of Draft Final Strategic Plan |
October 17 |
|
16 |
SJCOG Board Workshop |
Review/Approval of Draft Final Strategic Plan |
October 25 |